Ongoing grid upgrade to cause continued power disruptions until end of June – TCN 

image

The Transmission Company of Nigeria ,TCN, has announced an extension of the ongoing maintenance work on the Jos–Bauchi–Gombe 330kV single-circuit transmission line to facilitate the completion of the Optical Ground Wire OPGW, installation project along the corridor.

In a statement issuedweekend and signed by the General Manager, Public Affairs, Ndidi Mbah, TCN said the maintenance exercise, which commenced earlier this year will now continue until June 30, 2026.

According to the company, the extension became necessary to enable contractors complete the OPGW stringing project along the 276-kilometre Jos–Bauchi–Gombe transmission line axis.

TCN explained that the maintenance activities will affect electricity supply to customers served by the Yola Electricity Distribution Company ,YEDC, and Jos Electricity Distribution Company, JEDC, in Bauchi, Gombe, Damaturu and Maiduguri.

The company noted that affected customers will experience limited power supply between 9:00 a.m. and 6:00 p.m. from Thursdays to Sundays throughout the maintenance period.

It further

This post was originally published on this site.

RELATED ARTICLES

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -
Google search engine

Most Popular

- Advertisment -
Google search engine
- Advertisment -
Google search engine